Safari de Peaugres
Location
Peaugres (07)
Type of space
Wildlife park
Project description
Client initial brief
Our teams worked with the Safari de Peaugres to completely renovate their catering area and professional kitchen.
Challenges or constraints encountered
The project took 3 months to complete, including the asbestos removal phase. Our teams were working during the opening period, so we had to take into account the constraints associated with visitor traffic. Particular attention was also paid to the tranquillity of animals near the site, and the risks associated with their presence. We also aimed to complete the park’s illuminations before the Christmas holidays.
Solution proposed and implemented
Groupe Pagès carried out and coordinated all the work on this project:
- structural work
- structural recovery
- connection work and external works
- interior fittings
- professional kitchen
- bespoke furniture
Building work
Total project area
600 M2 including 200 M2 kitchen
Project duration
12 weeks
Testimony
“Respecting the environment, adapting to the site, managing visitor flows… The team rose to the challenge with flexibility and professionalism. The result blends in perfectly with the park’s surroundings.”
Arthur, Account Manager, Groupe Pagès